Site preparation guides

Site preparation before drilling rig shipment

What must be shared before shipment and be available on site so that installation and commissioning proceed as planned.

2 min read

Rear platform leg fabrication

To be shared in advance

  • Technical details of the truck for mounting: must be shared before production or site preparation.
  • Names of the personnel to be trained: if provided in advance, workwear and certificates can be prepared.

Provided on site by the buyer

On site, the buyer supplies a welding machine, oxy-fuel welding set, angle grinder, drills and similar tools.

On-site time

Estimated on-site time for installation, commissioning and training is 7 working days. The exact scope and fee are set in the quote.

In export projects

In export projects, Qawsar handles technical documentation, shipment planning, the acceptance process and field support together.

Technical scope, EXW delivery, optional services, and export and logistics terms are clearly stated at the quote stage. Shipping, freight, insurance, import and destination costs are assessed separately according to the relevant quote.